A food company has decided to install large-diameter duct piping due to the expansion of their manufacturing line. Since the piping will carry exhaust gases containing solvents, it is necessary to use stainless steel ducts. They have requested to keep costs as low as possible. Issues: 1. A φ500 stainless steel duct must be installed from the manufacturing building to the outdoor scrubber over a distance of 150m. 2. With stainless steel spiral ducts, leaks occur at the crimped joints. 3. If standard stainless pipe products are used, only thick-walled specifications are available, which increases costs and weight. 4. Since this work will be done simultaneously with other construction, it is necessary to devise a work schedule that fits within the construction period.